Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

10/4/13

Tom, Sebastian, Matt and Eric.

Installed the two sonics at SSW2 and SSW4 today, after much running up and down the crater sidewall to get the correct cables to plug into the motes.  Also installed a second 30W(?) solar panel at both sites.  These were scavenged from the solar panel stands at FLR.  FLR is now powered by 4 60W(?) solar panels.

...