  • Met with Electrician Tom and showed him the plug we need for CLAMPS.  He should be able to get it installed before CLAMPS arrives on 12 July.
  • Fully extended TT around 11:00 and left it (guyed) that way.  Noted that the tower near the balloon inflation shed is the same height, so not worried about aircraft
  • Reinstalled soil sensors – sensors about 11:30 – also training for Chris
  • Removed the previous extension cords that initially were providing power to TT
  • Matt did Leica scans of all the sensors, using a GPS-based coordinate system!!!
  • Isabel added ISS to the Ubiquiti network, which broke the ISFS link temporarily.  She'll probably be adding a separate blog post about this.

...