June 28, 2008
9:00-11:00am. Putting Put 1/16 in couplers to the transducers on the lower array. The tubing on the transducer is hard and the coupler cannot be inserted directly, a heat gun was used to melt the tubing in order to insert the coupler.
1:30-3:00 pm. Connecting Connected 1/4 tubing to the pressure ports
June 29, 2008
8:30-9:15 am. Connecting Connected 1/4 tubing to the pressure ports
8:30-9:30 am. Dug a hole for the reference cylinder
...
9:00-10:10 AM. Buried the reference cylinder. Covered it with a thermal blanket. Ready to test and take data.
July 1
12:00 - 1:00 PM. The straight and T couplers came in. Finished the reference sides of the transducers on the upper array.