Thus, we have asked INEGI if they can supply climbers for all of the towers, hopefully starting next week.  Obviously, we would provide all ground support.  We will meet tomorrow to see if we can organize into 3 crews, each with one or two INEGI climbers.  A secondary issue is that we would need INEGI climbers for all maintenance visits and tear-down as well.

Now for the good news: DTU has enabled AC power now for 4 of the tall masts.  After some work on the network, software updates for the DSMs that we hung in December, and enabling of DTU data, we now have 10 sites reporting.  There are two more 60m masts that require minor AC power fixes, but this needs to be done by the electricians.

...