The whole tower has all instruments on it and the cables/tubes are dressed.  We have a couple of tubes that are low that need to be strung and the lower dsm to be hooked up and then we can have Gordon test all instruments while I am here.  We still do not have power to the tower but now that ACDs gear is loaded and the trailer is put into it's spot we can start hooking up transformers and run power to tower.  We can do testing off of batteries for today but we should have power going soon to the tower.  

Gordon and Tom have arrived and they found the tower.  

The inlet on the tubes are hanging just by the Licor mounting bolt.  It seems to be far enough away from sonic/licor and pressure port.  Tom will have the final say on location today.  

Things to do:

Soils/radiation stand (tom)

lower dam (chris)

tower power(kurt)

fiber (john/gordon)

pond & lidar communications (john)