*** IOP last night - still need to launch the 10am sounding

At ISS1 Trailer

  • Weather is clear and very little wind
  • Winding down IOP#3
  • Visual inspection of site good

Profiler computer and rack

  • Spectra and dwell counter updating
  • Dashboard shows all green lights
  • Amp power at 0.207mW (RASS mode)

Data Manager Computer

  • Critical flag on Nagios for metcraxii/profiler_latency_lidar/dbs/rtd
  • Critical flag on Nagios for metcraxii/profiler_latency_lidar/los/rtd
  • Zeb plots updating
  • Connected to WindCube lidar and saw plots updating
  • Web plots up to date
  • No labels