Noon today was the (new) official end of operations.  This morning, Tim, Kurt, John, and I completed tear-down of far.

Since people had asked, these are my GPS locations at far (Sebastian said he took his own readings yesterday).

Postion

Latitude (N)

Longitude (W)

DOP

far tower

34d 58.007'

111d 03.182'

5m

rad stand

34d 58.002'

111d 03.174'

5m

soil plot

34d 57.997'

111d 03.172'

5m

In the afternoon, Tim again climbed with the other 3 of us on the ground to strip 6 of 8 levels from Rim.

End-of-day status (not <too> bad for a project that ended at noon!):

- Trailer: All computers packed; networking down (but not yet packed).  (Had to disconnect AP24, Hughes, and base DSM since cables ran through space needed for packing.)

- Far: Totally removed (except Utah SODAR)

- Rim: 6/8 levels & 2/2 DSMS removed

- Base: Windsonic & DSM still running (just on battery), data only saved locally

- Flr: Should be completely running, data only saved locally

- Near: Tower should be running, data only saved locally.  (No radiation or soil.)

- 449 site: Tower is up.

- Chris just arrived; Clayton leaves tomorrow.