Today:
- flagged stuff in the crop
- added a 3rd battery to relt
- finished the cable sleeving project
- fixed an issue with R plotting
We now (2 weeks into the project) have come to the end of our TODO list. A secondary list:
- get rid of trash/recycle (haven't found a recycle center yet)
- make a theodolite survey of equipment (had hoped to do when corn was harvested, but might be a while)
- move stuff in the other part of Ken's yard to storage
- connect up the remaining power monitors (waiting for cables from Rochell)
- clean radiometers
- take soil samples
In other news, the DTS fiber is now strung between the aux and main towers at uconv, so access may be an issue.