Today was warm with high clouds and some wind later on. 

Last night the 4am and 7am launches did not happen due to miscommunications and LAX not approving the launches. 

This morning while checking Nagios I noticed the all sky camera and CL31 at ISS3 had not reported data for a while. Lou and I spent the morning there troubleshooting. It seemed as if the computer was frozen or working extremely slowly, so we restarted it. I also did a hard restart on the CL31. We realized we both didn't quite remember how to restart the CL31 software so we contacted Gary and Isabel. Between the both of them and us physically in the trailer we were able to resolve the issues and data had started coming back in. 

ISS2 and ISS1 do not have any pressing issues. There is a hard drive filling up (81%) at ISS1 for the profiler however. 