First day for the entire crew in the field.  Everyone came so that different perspectives could be shared about tower operations.  All this was done at rsw04, which is now ready for power.  We powered it up with a battery for about 30min to check out everything.  (ARL now is using DTU's portable generator.)

Errors found and fixed at rsw04:

Back in the ops center:

Interacted a bit with both Samortecnica's 3-person crew and ARL's crew (saw Chris just before he left).  Samortecnica was working on rsw05, 06, 07 today.  ARL has the SW energy balance 10m tower up, though not completely connected; one 30m tower up; at least 3 other 30m towers are erect, but not yet telescoped to full height as their crew is adding instrumentation.  So...progress is being made!