Another day, another 2 towers.  One crew did tse10 on the east side of the valley, another tse07 on the west side.  What is important is that tse07 is our first solar-powered station and, as such, is the first to have continuous power.  Thus, TODAY IS OUR FIRST DAY OF OPERATIONS!!!  As part of the tse07 installation, we took a soil sample, which also should be the first to be used for Qsoil comparison.

Except for tnw07 (the 60m tower instrumented with DTU sensors), we have now installed everything that we "prepped" in December.  Tonight, I started prepping another 4 towers.

In other news:

Thus, a lot of activity is going on.