Create ESMF dev branch and define and create ESMF states
Ideal engineering time: 3 weeks
Start date: August 18th
Completion date: Jan 14th, 2007
Off-time during project: 5 days (script), 16-days (vaca), 4-days (sick)
Actual weeks on project: 16
Estimated lines of code: 6kl (MCT implementation has 5kl)
Actual lines of code: 15kl (including unit tests)
Factor: 5.0, 190 lpd
Create top level ESMF application driver for all components.