After a review of several issues amongst ourselves we:

Thus, ue, uw, and d are all at the same state of having 30' assembled on the ground, attached to a secure tilting base plate, and with permanent guys attached.  We can add the top 5' to each of these to finish up.  However, they can't be erected until we have guy anchor points that we are happy with.  We will retry Manta installation tomorrow with the remaining parts that are needed that Bob is bringing tonight.

We also assembled 20' of tower c (which does not have a tilting base plate) on the ground.  Again, it is waiting for guy anchor points to start going vertical.

We left the site at 12:30, having worked through intermittent rain.

Tony and William are on the way to Gunnison to return the UHaul.