Configuration

Four single hot-films will be deployed along with sonic anemometers on the t0 tower at heights of 0.5, 1.0, 2.0, and 4.0m.  They will be vertically oriented (measuring horizontal speed), mounted on probe supports attached to the sonic anemometer array.  Two bridge enclosures will each hold 3 bridges, but only two bridges in each enclosure will be used (this allows a bridge to be replaced, if needed, by another already in the enclosure).  A LabJack T7 housed inside the t0t(?) DSM will be used as an A/D to digitize the 4 signals from each of the hot films at approximately 2,000 sps.  Code is being written to archive these data in a nidas-compatible format synchronized to the GPS PPS timing signal along with 1-s averages to allow a quick monitoring of the data.  Ordinary coax cables with BNC connectors are used both between the probe support-to-bridge and bridge-to-LabJack.

Operation

Voltages will be monitored by looking at the 1-s average signals.  The normal range is about 1.5-4.0V.  If a probe is broken, the signal goes to about 4V (check!).  If a probe has to be replaced:

We only have 7 probes for the 4 positions for the entire experiment, so we want to be very careful to avoid accidental breakage!!

Supporting documents