• No labels

3 Comments

  1. Ivana Vu

    4/22/25

    -SAR

    -EMI


    4/23/25

    -Power & Access

    -Safety Briefing

    -Troubleshoot ILS interference issue found during EMI


    4/24/25

    -NoPower & Access (ILS troubleshooting)

    -Checked 2DS humidity: nitrogen purge not needed

    -Updated User Laptop Quick Guide (added to project setup folders)


    4/25/25

    -No Power & Access (avionics troubleshooting)

    -Made telescope Sun Cover

    -Installed bottom telescope bolt


    4/28/25

    -EMI #2

    -Verified GPS picks up satellites on Aeros


    4/29/25

    -Power & Access

    -PP01 & PP02

    -Made Top Aft Camera Sun Cover


    4/30/25

    -Power & Access

    -Conducted CDP Calibration

    -Resolved VXCEL issue

    -Resolved 2DS computer issue (screen lock out)

    -Added 2 grounding straps to L-2 Rack

    -Removed top cover of L-2 Rack


    5/1/25

    -Power & Access

    -PP03 & MC Training

    -Troubleshoot 2DS housekeeping data and DSM 305. No Camera this project.

    -Installed XChat and synced timeserver on L-2 aft-facing laptop (Biff’s laptop)


    5/2/25

    -PP04

    -Power & Access

    -Inspected PLWC (ohmed out elements, reseated cables, checked analog cable from wing to DSM)


    5/5/25

    -Power & Access

    -Container and ground equipment loaded/shipped

    -PDF-ed drawings

    -Updated database entries

    -Sent project PPE list

    -Changed Zero Air tank in Aft Rack

    -Changed FO3/CO inlet line from stainless steel to Teflon


    5/6/25

    -Updated N2 and Zero Air procedures on Startup checklist


    5/7/25

    -No Power & Access (avionics troubleshooting)


    5/8/25

    -No Power & Access (avionics troubleshooting)

    -Finalized packing list

    -Setup Tech iPad

    -Installed spare ADS server

    -Inspected radome lines for moisture (purged ADIFR and QCR lines with air)


    5/9/25

    -No Power & Access (avionics troubleshooting)

    -Changed PLWC element back to original

    -Made foam cover for L-1 rack (light block for in-flight use)

    -Updated 2DS checklist (keep Rx/Tx arm heaters off for entire project)

    -Installed FastTemp probe and updated Channel Setup Sheet (RTF1)


    5/11/25

    -Installed R-5 Right Camera power supply

    -Calibrated Fast Temp Probe

    -Resolved 2DS issues (True Air Speed and Time Stamp updating)

    -Added more light blocks to Dominique’s cameras


    5/12/25

    -Loaded final items in container (2DS, ladder, dry ice)

    -Resolved frosting on Zenith Camera window (scat tubing from air vent)

    -Swapped L-5 and L-6 laptops; configured for camera VNC’s


    5/13/25

    -Inspected radome lines (no moisture found)


    5/14/25

    -Updated ADS binder


    5/15/25

    -Tested SATCOM calling and texting from plane

    -Packed plane


    5/16/25

    -FF01: KBJC to KDSM


    5/17/25

    -HDD


    5/18/25

    -Power and Access

    -2DS humidity: 11%

    -Cleared QCR radome line of moisture

    -Cleaned 2DS and CDP lenses


    5/19/25

    -Transition to Night Shift


    5/20/25

    -Transition to Night Shift

    -RF01


    5/21/25

    -Power & Access

    -Cleaned 2DS and CDP lenses

    -Checked radome lines (clear of moisture)

    -2DS Humidity: 11.2%

    -PP05


    5/22/25

    -HDD


    5/23/25

    -Reseated DSM PPS cable and cleaned connector with Contact Cleaner

    -Cleaned 2DS and CDP lenses

    -RF02


    5/24/25

    -RF03


    5/25/25

    -RF04


    5/26/25

    -Power & Access

    -CDP Calibration (ADS Filename: 20250527CDP)

    -Changed Zero Air tank

    -Cleaned 2DS and CDP lenses

    -Checked radome lines (no moisture)

    -Cleaned Dewpoint Left head. Dewpoint flag was not receiving proper flow; re-installed flag and ensured flow; values between DPL and DPR are more consistent now

    -Cleaned 2DC lens; 3 diode values more consistent now at around ~2.4V

    -Catherine fixed VNC issue on Laptop 8 and Laptop 9

    -Taped radome holes and put on probe covers


    5/27/25

    -RF05


    5/28/25

    -RF06


    5/29/25

    -HDD


    5/30/25

    -Power & Access

    -Checked radome lines for moisture (completely dry)

    -Changed Zero Air tank

    -Catherine configured and tested 3 thumb drives, so they work on ADS station now

    -VNC on L-6 Rack view-only

    -Teresa removed NO Containment Vessel and is troubleshooting Fast Ozone instrument

    -PP06


    5/31/25

    -NO Containment Vessel swapped out at R-4 Rack

    -RF07 cancelled due to weather forecast not being ideal for data collection

  2. Kyle Holden

    6/7/25

    • Removed 2DS S/N 19.  Installed S/N 20.  Installed new desiccant, lubricated O-ring, cleaned lenses, and purged with N2 to 7% RH.
    • Cleaned DPR and DPL.
    • Purged radome lines.  No visible H2O.
    • Swapped out optical port purge N2 cylinder.
    • Inspected PPS distribution box.  That hole is just a hole.  No visual loose connections.  Installed and is working as before.  DSM303, DSM304, ADS rack GPDAQ PPS's all look good.  The bottom row must be bad.  Further diagnosis will be needed when we get back to RAF.
    • Started loading sea container.
    • CDP Cal:
      • ADS Filename: 8Jun25
      • Cleaned lenses and started calibration.
      • Cleaned 01:46
      • 2um       01:48
      • Cleaned 01:49
      • 5um       01:50
      • Cleaned 01:51
      • 10um     01:52
      • Cleaned 01:53
      • 15um     01:54
      • Cleaned 01:55
      • 20um     01:56
      • Cleaned 01:57
      • 30um     01:58
      • Cleaned 01:59
      • 40um     02:00
      • Cleaned 02:01
      • 50um     02:02
      • Done     02:03



  3. Kyle Holden

    13Jun25

    Blew out QCR for the ferry back to Broomfield.