CCSM Data Model v7 Project
Project Plan (obsolete – Dec 2004)
<html>
Implementation Schedule
Phase I ~ create working models which implement architecture, shared code, and a
uniform set of basic functionality.
A) requirements analysis wrt to basic/uniform functionality and framework (2 weeks)
B) choose an architectural design wrt basic + framework requirements (3 weeks)
C) implementation: detailed design, coding, debugging, unit-testing (4 weeks)
D) preliminary-system testing (3 weeks)
Phase II ~ improvements to scientific functionality
A) additional requirements analysis wrt to scientific functionality (2 weeks)
B) modify architectural design wrt science requirements (3 weeks)
C) implementation: detailed design, coding, debugging, unit-testing (4 weeks)
D) system and acceptance testing (3 weeks)
Resources:
Phase I: 838 man[hours (5.2 man]months) over 12 weeks
Phase II: 838 man[hours (5.2 man]months) over 12 weeks
Core team members: brian k, julie, nancy, mariana, brian e,
Other team members: erik, wei, george