Weather: Overcast morning with scattered cumulonimbus throughout the afternoon. No precipitation today but plenty of sunshine.
Over the past couple of days:
- Built 10m Upper Convergence Tower utilizing double screw anchors at each guy point
- Acquired remaining three 1 ton concrete blocks to use as guy anchor points(bringing the total to 6)
- Dug recessions at final positions to reduce cross section of blocks visible to instrumentation
- Rigged blocks with wire rope eye & eye slings to use as rated mount point for 20m tower guy wires
- Installed first section of both 20m towers and the six rigged blocks in their final positions
The anchor issue is now resolved, tomorrow we will resume building Lower Convergence Tower.