Weather: Overcast morning with scattered cumulonimbus throughout the afternoon. No precipitation today but plenty of sunshine.

Over the past couple of days:

  • Built 10m Upper Convergence Tower utilizing double screw anchors at each guy point
  • Acquired remaining three 1 ton concrete blocks to use as guy anchor points(bringing the total to 6)
  • Dug recessions at final positions to reduce cross section of blocks visible to instrumentation
  • Rigged blocks with wire rope eye & eye slings to use as rated mount point for 20m tower guy wires
  • Installed first section of both 20m towers and the six rigged blocks in their final positions

The anchor issue is now resolved, tomorrow we will resume building Lower Convergence Tower.