Blog from July, 2013

Soil Installations

TP01 Installation Note: The sensors were placed in the ground at the proper depth, but the transducer foil was oriented 90-degrees off, being flat rather than edge facing up.

See photos for some of the soil installations taken at/prior to teardown.   Note the branch at SoilB and the uncovered transducers prior to excavation.   Other photos are available on the project repository and will be posted to the web page when available.




Following the SOAS project, we tested each sonic in a zero-wind enclosure within the EOL temperature chamber, measuring wind component offsets and sonic temperature errors over the nominal range -30 C to 55 C.  The procedure is to warm the chamber up to 55 C and then slowly decrease the temperature linearly to -30 C, followed by slowly increasing the temperature back to 55 C.  The zero-wind enclosure holds two sonic heads on their sides (with the v-axis vertical) and electronics, one above the other and separated with a horizontal layer of rigid blue foam.  On the cool-down cycle, the atmosphere around the top sonic is unstably stratified (cold enclosure lid above warmer air) and that around the bottom sonic is stably stratified (cold enclosure bottom below warmer air).  The opposite is true during the warm-up cycle.  Both the wind component data and the sonic temperature data have significantly less variance when the air is stably stratified, and thus we use data from the bottom sonic during the cool-down cycle and data from the upper sonic during the warm-up cycle.

The following table shows wind component offsets as okay if the u and v offsets are less than +/- 4 cm/s and the w offsets less than +/- 2 cm/s.  If the zero wind offset exceeds these thresholds, the table lists the temperature range of the over-limit offset and the largest amplitude of the offset.  The plots of offsets versus temperature can then be examined to determine the exact nature of the offset.

The last column relates to the following project, METCRAX, in October 2013.  The operating temperature range for night-time warm-air intrusions into the crater is on the order of -10 to +20 C.  The last column notes whether or not the sonic is suitable for that temperature range.  Several sonics not used in SOAS tested okay post-SCP.

SN

Height

EOL Cal

CSI Cal

u

v

w

METCRAX?

0536

 

8/1/13

6/27/12

ok

ok

ok

OK

0537

 

8/1/13

6/21/12

ok

ok

ok

OK

0538

8 m

7/25/13

10/17/12

32 - 49 C
-7 cm/s
@43 C

46 - 49 C
-7.3 C
@ 49 C

44-46 V
-2.5 cm/s
@ 45 C

OK

0539

 

8/2/13

6/20/12

ok

ok

ok

OK 

0540

 

 

2013 recal

 

 

 

OK

0671


8/3/13

6/28/12

ok

ok

ok

OK 

0672

32 m

7/26/13

10/10/12

35 - 49 C
+8 cm/s
@ 47 C

36 - 49 C
-7.4 cm/s
@ 49 C

ok

OK

0673

26 m

7/25/13

7/18/12

ok

25 - 44 C
+6 cm/s
@ 39 C

20 - 50 C
-3 cm/s
@ 34 C

OK

0674


7/29/13

8/13/12

ok

ok

ok

OK

0677

 

8/2/13

6/17/12

ok

16 - 30 C
-7 cm/s 
@ 23 C

ok

Requires
CSI recall

0720

RAL

7/31/13

12/31/11

ok

ok

ok

OK

0738

RAL

8/1/13

5/12/10

17 - 25 C
-4.8 cm/s
@ 21 C

10 - 45 C
-8 cm/s
@ 20 C

26 - 42 C
+2.4 cm/s
@32 C

Returned to
RAL

0739

RAL

8/1/13

8/18/10

46 - 55 C
> +8 cm/s

ok

48 - 55 C
+2.8 cm/s
@ 55 C

OK

0740

RAL

7/31/13

8/28/12

ok

ok

26 - 36 C
-2.4 cm/s
@ 31 C

OK

0800

14 m

7/29/13

6/19/12

ok

10 - 35 C
+8 cm/s
@ 21 C

17 - 53 C
-3.6 cm/s
@ 45 C

Requires
CSI recal

0853

 

8/2/13

6/21/12 

ok

ok

ok

OK 

0855

 

8/3/13

9/12/12 

-13 - 1 C
-4.4 cm/s
@ -11 C

ok

44 - 49 C
-2.8 cm/s
@ 47 C

Marginally
OK

0856

 

 

2013 recal

 

 

 

OK

1117

 

 

2013 recal

 

 

 

OK

1119

2 m

7/26/13

8/9/12

ok

49-53 C
+7 cm/s
@ 53 C

1 - 44 C
-3 cm/s
@ 17 C

Marginally
OK

1120

 

 

2013 recall

 

 

 

OK

1121

20 m

7/26/13

12/8/11

-14 - 24 C
-11 cm/s
@ -9 C

-14 - 44C
-9.5 cm/s
@ -7 C

-15 - 49 C
-5.6 cm/s
@ -9 C

Requires
CSI recal

1122

44 m

7/26/13

12/8/11

28 - 53 C
+5.8 cm/s
@ 36 C

49 - 53 C
-4.3 cm/s
@ 53 C

48-53 C
-2.7 cm/s
@ 53 C

OK

1123 

 

 

2013 recal

 

 

 

OK

1124

 

8/2/13

7/19/12

ok

ok

ok

OK

1244

38 m

7/30/13

 

-25 -  49 C
+17 cm/s
@ 27 C

11 - 30 C
+5.5 cm/s
@ 23 C

18 - 42 C
+6 cm/s
@ 28 C

Requires
CSI recal

These are the mote associations with the radiometer-booms at teardown.  Some changes from setup noted.

See also entry from June9th "Sensor Locations and Serial Numbers."

Level

Mote

PAR

IRT

Wetness

 

8m

SN1

1530
wand

4078-1

023

irt changed from original 3577-4

14m

SN17

1529
wand

3389-1

032

irt changed from original 4078-3

20m

SN2

1893
wand

3577-4

036

changed irt on 7/13

26m

SN3

1892
wand

3577-2

026

 

32m

SN8

6951
apogee
single

3577-3

022

irt changed from original 3389-3

38m

SN19

4-comp

 

 

 

DONE

July 20, 2013

We are all packed and site is cleaner than when we left it.  Good bye, SOAS.

Tower Down Base Gone

July 19, 2013

The whole tower is down and all gear has been removed from the forest...including power cable.  Base Trailer has been shipped out and all we have is to do is pack the Penske.

Base Packed

July 18, 2013

Base Trailer is packed and ready for moving.  We will stage it over by the old gov't buildings so Trailer Transit will not have to deal with any nasty conditions.  The tower is down to 30' and all sections have been cached by the old gov't buildings.

Lightning protection has been removed from the SEARCH site.  Hardhats, first aid kit and safety glasses have been brought back to the AABC site for shipping. 

Tower Removal

July 16, 2013

Got down to 80' on tower removal.  This includes anchors and chemistry tubes.  

Tower Undressed

July 16, 2013

We have removed all sensors and brackets from the tower today.  Fiber has been pulled and wound up on spools.

High Fives!

SHUTDOWN!

July 16, 2013

~9:00am CDT

Shutting down all systems.   Good night, SOAS.

Tower Climbed

July 15, 2013

~11:30am CDT

Tower was climbed with a student tour.  Lasted about 15 minutes.

15Jul13

From ~12:15 - 15:30 we had the power down at the tower site, and thus the network link as well.   NO DATA LOSS: Local data storage remained up on the dsm's and data transfer should happen as normal tonight.

This was done as the ACD / Tram trailer were loaded and hauled out.   Kerry Slaven showed up to help and they brought their Penski so we took advantage and had the ACD eqpt. loaded for shipment early.   While doing so, we then pulled our big transformers and put them in the Tram trailer in addition to the ACD overflow in preparation for shipping.

Power was re-wired to the small transformers and the network comms came back normally.

15July13 first look .... edits lost/computer problem, leaving for base and tram trailer extraction.   Last day of project

Re-entering what i recall when looking hour+ ago..... 

 

 

 

Personnel

jm,cg

Kurt, Rudy arrived for teardown

Weather

 

Forecast is for 40% isolated showers with high in mid 80's.    Rain last night at ~9-11pm CDT (2-4z)

Other

 

ACD operations are over and Tram trailer is going to be pulled today.

System

ok

Cockpit

 

vpn

vpn ...  

 

df

/media/usbdisk %  /scr ..%  Backup .... / ..% 

DSMs

ok

low,mid,high, gps all ok. 

 

ok 26m

26m sonic had troubles and continuing since rains last night.   Others appear ok.

WndSpd/Dir

ok

 

H2O, CO2

ok

All Licor7500 diags all remain normal.

TRH

ok

 

P

43m

43m problems continuing.  

Rad

ok

 

Tsfc

ok

8m tsfc may be having troubles

Wetness

ok

 

Soil

ok

tsoila 4.4cm bad.

VmoteRad

ok

 

Webcam


 

Pond

ok


Sodar

 

 

Tower Ride OPEN

July 14, 2013

11:30 - 1:00pm CDT

Took three students up the tower for a show-and-tell.  The ride price was $10 for 10 minutes, with additional minute(s) at 10cents.

20m IRT outage

20m Tsfc out from ~ 12July 2:00 - 14July 9:30

The old sensor filled with water apparently from the back/bulgin side.

The new sensor installed 7/14 ~9:30 but not seen in cockpit or covars.   Looking directly at the mote using 'mp=1' dsm-printable it is reporting.   Its i2c address is 0x3c, serial number 1.   The xml may be looking for a different address.

14jul13 pm update

 

 

 

Personnel

jm,cg

 

Weather

 

Forecast is for 80% chance tstorms high in low-mid 80's.    Rain last night at ~9pm CDT (2z)

Other

 

Tower climbing from 9:30-13:00.  First we took photos hoping to document the sensors/heights; then students showed up for an ISFS orientation and Chris helped 3 of them climb the tower sequentially.

System

ok

Cockpit ok

 

vpn

vpn not working from base    data getting through.  

 

df

/media/usbdisk 32%  /scr 80% backup 7% / 25% 

DSMs

ok

low,mid,high, gps all ok.   Vdsm mostly ok but pond a/c went out:

Sonics

ok

All sonics are up, good diags and normal until rain at roughly 14-15CDT

WndSpd/Dir

ok

 

H2O, CO2

ok

All Licor7500 diags all remain above 240: normal operation.

TRH

ok

 

P

43m :-(

43m problems continuing.  

Rad

ok

 

Tsfc

ok

20m tsfc down.   New sensor installed ~9:30 but not seen in covars or covars.   Looking directly at the mote using 'mp=1' dsm-printable it is reporting.   Its i2c address is 0x3c, serial number 1.   The xml may be looking for a different address.

Wetness

ok

 

Soil

ok

tsoila 4.4cm bad.  Swapped battery on tsoil.b

VmoteRad

ok

 

Webcam

ok

 

Pond

ok

AC power is out and running off battery which is draining steadily.   Power strip in sodar distribution box was tripped and their air conditioner was off.   Turned back on

Sodar

ok

Hearing normal pinging, but the air conditioner was off until about 13:30