Setup for the IOP phase continues.  Today Emily and Geraint got the NCAS profiler working around midday - however after about an hour operation a fault developed which is being diagnosed with the assistance of the manufacturer.  It may be a temperature related issue since there may be a problem with AC on the system.  The hour of measurements did reveal significant ground clutter, despite being surrounded by a embankment on two sides (east and north) and the Operations Centre building to the west.  The south side is open to hills 1 - 2km away and we appear to be getting significant clutter from those.  We plan to build a clutter fence on this side over the weekend. 

Tomorrow an office trailer is due to arrive at the sounding site, along with Helium.