Today's status:

In general, pretty good by now so John and Ling return today.  (Kurt remains alone for a bit longer.)  Kryptons are being recalibrated in Boulder with shorter pathlengths and will be tested through serializers retrieved (today) from Manitou.  They will be installed by Tom and Gordon just prior to operations 29/30 Nov.  Fixes to the SPN1 and TP01 should also be straightforward.  Problems with Tsoils seem to be caused by inadequate conformal coating of the boards.  We'll probably just apply nail polish to fix.

Site

Battery
&Solar

Sonic

Krypton

Baro

TRH

Rad

Soil

Soil.aux

Precip

Shadowband

Prop

1

ok

ok

not installed

ok

ok

ok

ok

some Tsoil bad

not planned

SPN1 in Boulder
(A/D found bad)
Licor ok

ok

2

lowest

ok

not installed

ok

ok

ok

ok

not planned

not planned

not planned

not planned

3

ok

ok

not installed

ok

ok

ok

ok

not planned

ok

not planned

not planned

ok

ok

not installed

ok

ok

ok

ok

not planned

ok

not planned

not planned

5

ok

ok

not installed

ok

ok

ok

ok

Tsoil ok
Qsoil erratic
Gsoil ok 
TP01in Boulder
(will be reprogrammed)

not planned

not planned

not planned

6

ok

ok

not installed

ok

ok

ok

Tsoil profile kinked

ok

ok

not planned

ok

7

ok

ok

not installed

ok

ok

ok

ok

not planned

not planned

ok

not planned