Weather: Cumulus and comfortable temperatures for the past couple of days. The swale continues to dry out and firm up.
Tasking for 09/10 & 09/11:
- (09/10)- Installed P2, P3 & P4 sites
 - (09/10)- Determined location for Aux Towers and solar panels
 - (09/10)- Staged power infrastructure at prospective final locations
 - (09/11)- Instrumented Release Tower
 - (09/11)- Continued to clean out Penske for return on Friday
 
Tomorrow we plan on instrumenting the Initiation Tower and begin powering the 10m & 20m towers.