Said goodbye to the ISS team, who are essentially done with set up.  Now onsite is Gary, Steve, Dan, Chris, Tony.

Temperatures were above freezing some of the day, so things started becoming muddy.

Split into 2 teams.

  • Tony/Chris (and some of Dan) finished (question) install of MW, including user sensors and power connection.
  • Steve/Dan (and some of Sebastian) mostly finished the surface installation at PRS, including:
    • getting power going
    • installing Sebastian's ceilometer and webcam
    • preparing radiometer stands and placing them into position for the intercomparison
    • mostly instrumenting the Rohn tower (still needs 1m TRH and replacement of a broken pressure tube)
  • In addition, Sebastian/Eric/Alexei reported that they positioned at least one darkhorse at DCS

We're getting there, but a lot of busy work to do things right!


  • No labels