Today was a late start due to rain -- we started work about noon and ended about 5PM so that Kurt could run into town for misc. hardware. Nevertheless, in these 5 hours we erected all but one of the A towers (since A17's parts couldn't be moved up the gully due to wet ground), the C tower, and the first 3 (of 7 total) sections of the main tower. We also placed the rad stand. So...only 5 more tower sections to go!
Weather is expected to be good into the weekend. We expect the base trailer to arrive tomorrow morning.