Yesterday, Tim, Kurt, John, Chris finished stripping rim and removed the top 40'.  I was given the day off to explore a larger hole in the ground.

Today plan to split into 2 groups: 1 to finish dismantling rim and the other to strip near.

Sat. Evening update:

- 449 tower totally stripped

- Rim dismantled/pieces retrieved/ready for helo.  This makes us completely ready for helo ops (3 days before helo arrives)

- Near totally stripped, ready to be dismantled (also need to retrieve solar panels and rad stand).  Data taking stopped about 10:00AM.

- Base still has a wind sonic mounted (but not taking data since Thursday).

Sun. Afternoon update:

- Removed top guys/beacon/first tower section from near, before winds became intolerable

Mon. Afternoon update:

- Removed the rest (160') of near (despite "breezy" winds) with a 5-person crew.  Site now totally clear.

- (Towers still up at 449 and base.  Base still has its (disconnected) 2D sonic on the top.) 